UPS never required detailed inspection of part that failed before engine flew off plane that crashed

UPS never required the detailed inspections needed to spot the problem that led to an engine to fly off one of its planes before it crashed even after Boeing recommended it years earlier, according to new documents posted Wednesday by crash investigators.

But UPS said in its own submission to the National Transportation Safety Board that the reason it never required those enhanced bearing inspections inside the pylons that hold the engines to the wings of its MD--11 freighters is because Boeing said incorrectly that the failure of those bearings wouldn’t jeopardize the safety of flight. And the enhanced inspections were never required.

The plane crashed last fall while accelerating down the runway at Louisville’s Muhammad Ali International Airport, killing killed all three pilots and 12 people on the ground. Twenty-three more were injured.

The failures that kept mechanics from taking a close look at the key parts securing the engines to the wings were highlighted at two days of investigative hearings on the crash in May, but the documents released Wednesday provide additional details.

The NTSB might not publish its final report on the cause of the fiery crash that happened as the UPS plane was trying to take off in Louisville, Kentucky, last November until late this year or possibly early next year. But UPS said it’s clear “once the pylon separated from the aircraft, the crash was inevitable.”

                        Related Stories
                    
                

        
    
    
    
    







    
        

                
                    



    
        


  




    




    




    




    




    




    




    




    



    




    
    
    
    

    

    





    
        

            
            
            Investigators find no evidence of engine failure in fiery crash of skydiving plane that killed 12
        

    

  

    

    
    







    
    
        
        
    
    
    
    
        

            3 MIN READ
        

    
    
    
    







    

    

    

    

    




                
            

    
        

                
                    



    
        


  




    




    




    




    




    




    




    




    



    




    
    
    
    

    

    





    
        

            
            
            A passenger jet reported hitting a drone approaching NY. A helicopter had a near miss hours later
        

    

  

    

    
    







    
    
        
        
    
    
    
    
        

            3 MIN READ

11

            Jets were 300 feet apart in Boston close call that forced Delta flight to abort landing, expert says
        

    

  

    

    
    







    
    
        
        
    
    
    
    
        

            1 MIN READ

30

Boeing and Federal Aviation Administration officials acknowledged during the hearings that they misunderstood the risks related to the potential failure of a steel bearing and metal sheath in the engine mount before the crash, not realizing that it could lead to the lugs that secure engines to an MD-11’s wings breaking. The bearings are tucked deep inside near the pylons, so problems are hard to spot without removing each engine for detailed inspections.

Read More 

Aviation safety expert Jeff Guzzetti said the actions of Boeing, UPS, FAA and the maintenance company STE San Antonio Aerospace all contributed to this crash.

“There’s just lots of subtleties and semantics that these four entities are using. But in the end, this got missed and to some degree, all four have some role to play in that,” said Guzzetti, who used to investigate crashes for both the NTSB and FAA. “Safety is a shared responsibility, and I think the NTSB’s task now is to apportion that responsibility.”

**Sign up for Morning Wire:**
Our flagship newsletter breaks down the biggest headlines of the day.








  

    Email address
    
  

  
    Sign up
  




  
    
    
      By checking this box, you agree to AP's
      Terms of Use
      and acknowledge that AP may collect and use your data pursuant to our
      Privacy Policy.

Failure of key part securing the engine never identified

Chris Hentz, who is Vice President of STE San Antonio Aerospace, said UPS only required its mechanics to check for corrosion and not for signs of bearing failure. But Hentz and UPS both pointed out that even as Boeing said “changes to the inspection requirement of the spherical bearing were warranted” the planemaker said in the same letter that the existing inspection requirements were sufficient.

Hentz said in his letter that Boeing “stated that while the MD-11 inspection intervals and requirements for an inspection of the aft bulkhead were sufficient, changes to the inspection requirements of the spherical bearing were warranted to ensure that the migration of the outer race would be reliably detected and identified during inspection.”

UPS said that even though Boeing developed an enhanced inspection procedure that it added to the MD-11 maintenance manual, the planemaker never added that procedure to its federally approved maintenance schedule that would have required it.

“Relying on Boeing’s representations that the issue was not safety-of-flight and that existing MPD inspections were sufficient, UPS determined that no additional changes to its maintenance program were necessary beyond what was already being performed.” the package delivery giant said.

Past problems didn’t trigger alarm

At one point, Boeing even successfully petitioned the FAA to extend the schedule for required inspections from once every 19,900 cycles of takeoffs and landings, to once every 29,260, so that airlines could complete more of the major maintenance tasks simultaneously, with less down time.

The planemaker sought the change even after receiving reports about seven of the flaws in the bearings well before the planes had reached their original inspection limits. In the years after the schedule was relaxed, three more instances were discovered before the crash.

The UPS plane that crashed after losing its engine had flown 21,043 cycles, so it should have been thoroughly inspected under the original schedule. There has been only one other crash, decades earlier, involving a similar plane model losing an engine, but that one was blamed on improper maintenance and not the same flaw.

FedEx and other operators of these MD-11s reported at least 10 other instances of failures of these bearings or the parts that hold them in place over the years before the UPS crash. But it’s not clear what these other operators might have been doing differently in their maintenance.

FedEx resumed flying its MD-11s in May after the FAA approved Boeing’s plan to ensure their safety. The engine mounts were closely inspected following the November crash, and going forward the spherical bearings will be replaced regularly, after every 4,000 cycles of takeoffs and landings. UPS decided to retire all of its MD-11s early after this crash.

This page may contain third-party content, which is provided for information purposes only (not representations/warranties) and should not be considered as an endorsement of its views by Gate, nor as financial or professional advice. See Disclaimer for details.
  • Reward
  • Comment
  • Repost
  • Share
Comment
Add a comment
Add a comment
No comments
  • Pinned