Bitcoin mining company Hut 8 announced that it has signed a 15-year, $9.8 billion lease agreement for the first phase of its Beacon Point AI data center campus in Nueces County, Texas, involving 352 MW of IT capacity.


The tenant is an undisclosed high-investment-grade company that will use the space to support large-scale AI training and inference workloads.
The agreement increases Hut 8's signed AI data center capacity to 597 MW, with the total value of the base term contracts approximately $16.8 billion, and an average annual net operating income of about $1.1 billion.
AEP Texas has signed interconnection agreements for the entire 1,000 MW campus, with preliminary power connection expected in the first quarter of 2027, and the first data hall is expected to be delivered in the third quarter of the same year.
(Decrypt)
Xem bản gốc
Trang này có thể chứa nội dung của bên thứ ba, được cung cấp chỉ nhằm mục đích thông tin (không phải là tuyên bố/bảo đảm) và không được coi là sự chứng thực cho quan điểm của Gate hoặc là lời khuyên về tài chính hoặc chuyên môn. Xem Tuyên bố từ chối trách nhiệm để biết chi tiết.
  • Phần thưởng
  • Bình luận
  • Đăng lại
  • Retweed
Bình luận
Thêm một bình luận
Thêm một bình luận
Không có bình luận
  • Ghim