Cenovus Plans Major Turnaround at Lima, Ohio, Refinery in Second Half -- OPIS

robot
Abstract generation in progress

Cenovus Energy is planning a major turnaround at its 185,000 b/d Lima, Ohio, refinery during the second half of the year, which is expected to reduce annualized throughput by 20,000 b/d to 24,000 b/d. The company’s overall maintenance schedule will impact U.S. refining throughputs by 35,000-45,000 b/d in Q3 and 40,000-50,000 b/d in Q4. This follows the successful completion of a 59-day turnaround at its Toledo refinery ahead of schedule in Q1.